Three requirements: be in the service area, be included in the district, and acquire a water tap.
  1. Be in the service area

    Your property must be inside the district’s approved service area.
  2. Be included in the district

    Non-members petition for inclusion before buying a tap.
  3. Acquire a water tap

    Permit, cross-connection agreement, main extension if needed, and fees.

1. Must be in the service area

The district has a defined boundary approved by intergovernmental agreement with the City of Lafayette and Boulder County Commissioners, and approved by the District Court. It roughly follows Apollo Estates, Benchmark Estates, Panorama Park and Paragon Estates.

A property inside the service area may or may not be “included” in the district. If the service area itself must be expanded to include a property, a much lengthier and more costly process is required.

District boundary mapOpen full-size map in a new tab

2. Non-district member: inclusion

Complete the Inclusion Petition, have it notarized, and mail it with your check for the fees, a copy of your property deed, and a survey or Improvement Location Certificate to the President at the address shown.

Inclusion process

The Board schedules an Inclusion Hearing at a regular monthly meeting and lets you know the date. You don’t have to attend, but it can help if there are questions.

  1. If the Board decides inclusion is in the district’s best interest, it votes to include you.
  2. The Board submits the inclusion to the District Court for approval.
  3. If approved, you are notified that you are a member of the district.
  4. If a Water Tap Permit Request and fees were submitted with the inclusion request, the tap is processed.
  5. The Boulder County Assessor updates property tax records to show the property is in the district.

Tap availability is not guaranteed

The City of Lafayette currently has no restrictions on issuing taps within the district, but it placed a moratorium on new taps during the last drought. The district will verify availability at the time of inclusion. It is the owner’s decision to acquire a tap then or later, knowing one may not be available later.

3. Acquire a tap

  1. Complete the Water Tap Permit form.
  2. Complete a Cross-Connection Agreement — a promise not to connect any other water source to the district’s system, a primary requirement of the City of Lafayette.
  3. If there is no water main in the street in front of your property, pay to extend the main to your property line.
  4. Pay the necessary fees.

Tap and installation fees

You pay the district’s and the City of Lafayette’s tap fees (based on meter size) plus the actual cost of installing the meter pit. The meter is usually placed near your property line next to the main; other locations can be accommodated within reason, possibly at extra cost.

After the meter is in, a licensed plumber or contractor makes the connection from the meter to the house at your expense, monitored by the district’s operators. Only two pipe types are allowed:

  1. Type K copper pipe.
  2. HDPE pipe conforming to ANSI/AWWA C901 (latest edition), PE 3408, DR 9, pressure class 200, listed for potable water under NSF 61, with a 12-gauge single-strand copper tracer wire attached with 2-inch PVC tape.

Reimbursement when a main is extended

You are the first user of a new extension

Other customers may later use the extension you paid for, so all parties enter into a Reimbursement Agreement. You are repaid part of the cost, prorated by distance.

You use someone else’s extension

The district will tell you if a Reimbursement Agreement applies, and the amounts and payees. Reimbursements must be made before water is provided.